CITY of RAPID CITY Agenda Item Summary |
|||
|
|||
Meeting Date: 6/30/2015 |
Planning Commission: 6/25/2015 |
||
Staff Contact: Fletcher Lacock, Current Planner II |
PW Committee or L&F Committee: 6/30/2015 |
||
Petitioner: Ferber Engineering Company for Black Hills Corporation |
City Council 1st Reading: 6/15/2015 |
||
Location: In the southwest quadrant of the intersection of Catron Boulevard and Les Hollers Way |
City Council 2nd Reading: 7/20/2015 |
||
Agenda Title: |
|||
15VR003 - Vacation of Right-of-Way |
|||
Summary: |
|||
The applicant has submitted a Vacation of right-of-way application for a portion of Catron Boulevard right-of-way. In addition, the applicant has submitted a Final Planned Development Overlay to construct an office complex for the Black Hills Corporation. The area that the applicant is proposing to vacate is currently a drainage channel that accommodates drainage from the Catron Boulevard right-of-way and will be incorporated in the on-site drainage pond for the proposed development. The applicant has indicated that an area inlet within the remaining right-of-way will be constructed to accommodate the right-of-way drainage. |
|||
Funding Source & Fiscal Impact (if applicable): |
|||
N/A |
|||
Recommendation: |
|||
Action: Approve Notes: Planning Commission recommended approval: 6/25/2015 |
|||
Options: |
|||
N/A |
|||
Attachments & Links: |
|||