CITY of RAPID CITY Agenda Item Summary |
|||
|
|||
Meeting Date: 1/23/2014 |
Planning Commission: 1/23/2014; 1/9/2014; 12/5/2013 |
||
Staff Contact: Fletcher Lacock, Current Planner II |
PW Committee or L&F Committee: N/A |
||
Petitioner: Davis Engineering, Inc for Chapel Lane Water Company |
City Council 1st Reading: N/A |
||
Location: At the current western terminus of Copper Hill Ridge |
City Council 2nd Reading: N/A |
||
Agenda Title: |
|||
13PD049 - Final Planned Development Overlay to construct a water reservoir |
|||
Summary: |
|||
The applicant has submitted a Final Planned Development Overlay to construct a water reservoir on the above legally described property for the purposes of improving the Chapel Lane Water Association’s water system and to increase fire flows. The applicant has stated that the new reservoir will be approximately 30 feet in diameter, 57 feet high and will be painted “environmental green”. To date, information has not been submitted that supports the need or identifies the benefit for the proposed water tower. In addition, information has not been submitted that supports that the location is where the water tower must be located, as requested by the Planning Commission. |
|||
Funding Source & Fiscal Impact (if applicable): |
|||
N/A |
|||
Recommendation: |
|||
Action: Continue to the February 20, 2014 Planning Commission meeting. Notes: Continued from the January 9, 2014 Planning Commission meeting. Continued from the December 5, 2013 Planning Commission meeting. |
|||
Options: |
|||
N/A |
|||
Attachments & Links: |
|||
|
|
||