May 21, 2012 - No. PW051512-23 – Acknowledge Report - Update on Horace Mann Pool.

July 2, 2012 - No. PW062612-19 – Acknowledge Final Report on Horace Mann Park Pool Replacement Feasibility Study.

July 16, 2012
- No. PW062612-19 – Final Report on Horace Mann Park Pool Replacement Feasibility Study.

Pool Study Analysis (also attached to 7/16/12 documentation)

Vision Fund Spreadsheet - Adjusted to reflect 8/30/12 recommendations

Horace Mann Pool Provision A Spreadsheet


Vision Fund Committee Recommendation:
Approve Option A, with additional funding, for the Horace Mann leisure pool in the amount of $5.1 Million for FY2015

 

 

Horace Mann Park Pool Replacement Feasibility Study