Authorize Mayor and Finance Office to Sign an Agreement between the City of Rapid City and Advanced Engineering and Environmental Services, Inc. (AE2S) for Professional Services for Meade/Hawthorne DBDP-Element 47 and South Ridge Road Sanitary Sewer Improvements, Project No. 15-2306, CIP# 50758, in the amount of $51,186.50.

Summary:

Inadequate sizing of existing stormwater drainage facilities are causing localized flooding and non-conforming sanitary sewer service lines conflict with construction of new drainage facility.

Funding Source & Fiscal Impact (if applicable):

 

Fund

Cost Center

 

Fund

Cost Center

Stormwater

Replace/Improve

 

 

 

Wastewater

Replace/Improve

 

 

 



Recommendation:

Action: Choose an item. Approve

Notes:  This contract is authorizing AE2S to complete final design services for recommendations provided in Technical Memorandum #14 for the Mount Rushmore Road Utility Reconstruction Project No. 11-1926. This project is from work completed under the Mount Rushmore Road project, which AE2S was selected to complete. The new project number assigned to this contract is for funding purposes and construction management.