CITY of RAPID CITY

Agenda Item Summary

 

Bid Opening Date: December 1, 2015

City Council Hearing: December 7, 2015

Staff Contact: Sara Odden

 

 

 

Agenda Title:

Approve award of Total Bid for East College Avenue and East Custer Street Reconstruction - Milwaukee to Racine, Project No. 14-2211 / CIP No. 50916 opened on December 1, 2015, to the lowest responsible bidder, Highmark, Inc., in the amount of $1,630,445.61.

Summary:

Reconstruction of sanitary sewer mains, water and sanitary sewer service lines and cathodic protection to existing water mains in College Ave and Custer Street from Milwaukee to Racine.  Reconstruction of the street and curb and gutter is also included.

Funding Source & Fiscal Impact (if applicable):

 

Fund

Cost Center

 

Fund

Cost Center

Streets

8910

 

Water

933

Drainage

8911

 

 

 

Wastewater Improvement

833

 

 

 


Budgeted      Not Budgeted

Recommendation:

Award:  Total Base Bid in the amount of $1,630,445.61 to Highmark, Inc.

 

Notes:

City Council Options:

 

Attachments & Links:

Bid Award Summary

Bid Opening Summary

Project Location Map

 

 

 