CITY of RAPID CITY Agenda Item Summary |
|||||||||||||||||||||||
|
|||||||||||||||||||||||
Bid Opening Date: September 29, 2015 |
City Council Hearing: October 5, 2015 |
||||||||||||||||||||||
Staff Contact: Lt. Tim Weaver RCFD |
|
||||||||||||||||||||||
|
|
||||||||||||||||||||||
Agenda Title: |
|||||||||||||||||||||||
Approve award Alternate 1, Total Bid for the Skyline Wilderness Area Wildfire Mitigation Project project No. CC100515-02.1 opened on September 29, 2015, to the lowest responsible bidder, Bighorn Tree Services, LLC in the amount of $62,997.04. |
|||||||||||||||||||||||
Summary: |
|||||||||||||||||||||||
This is to authorize RCFD to award the bid to finish the Skyline Wilderness Area Wildfire fuel thinning project. The original contractor was terminated by the city. A new contractor is needed to complete the approximately 24 Acres left in the original project scope of work. Project to be completed by March 2016. |
|||||||||||||||||||||||
Funding Source & Fiscal Impact (if applicable): |
|||||||||||||||||||||||
☒ Budgeted ☐ Not Budgeted |
|||||||||||||||||||||||
Recommendation: |
|||||||||||||||||||||||
Award: Alternate 1 Total Bid for entire project of 23.225 acres in the amount of $62,997.04 to Bighorn Tree Services LLC . Notes: |
|||||||||||||||||||||||
City Council Options: |
|||||||||||||||||||||||
|
|||||||||||||||||||||||
Attachments & Links: |
|||||||||||||||||||||||
|
|||||||||||||||||||||||
|
|
|
|||||||||||||||||||||
|
|
|
|||||||||||||||||||||