CITY of RAPID CITY Agenda Item Summary |
|||||||||||||||||||||||
|
|||||||||||||||||||||||
Bid Opening Date: July 28, 2015 |
City Council Hearing: August 3, 2015 |
||||||||||||||||||||||
Staff Contact: Sara Odden |
|
||||||||||||||||||||||
|
|
||||||||||||||||||||||
Agenda Title: |
|||||||||||||||||||||||
Approve award of Total Bid for 9th Street Reconstruction – Columbus to Fulton Street , Project No. 14-2208 / CIP No. 50959 opened on July 28, 2015, to the lowest responsible bidder, Mainline Contracting, Inc., in the amount of $2,417,485.66. |
|||||||||||||||||||||||
Summary: |
|||||||||||||||||||||||
Reconstruction of water mains, sanitary sewer mains, service lines and storm sewer in 9th Street from Fulton St. to Columbus St., Fulton St. from Mt. Rushmore Rd. to approx. 150' west of 9th St., and South St. from Mt. Rushmore Rd. to 9th St. Storm sewer install in 9th St. from Columbus to Kansas City St. Reconstruct street and curb and gutter also included. |
|||||||||||||||||||||||
Funding Source & Fiscal Impact (if applicable): |
|||||||||||||||||||||||
☒ Budgeted ☐ Not Budgeted |
|||||||||||||||||||||||
Recommendation: |
|||||||||||||||||||||||
Award: Total Base Bid in the amount of $2,417,485.66 to Mainline Contracting, Inc.. Notes: |
|||||||||||||||||||||||
City Council Options: |
|||||||||||||||||||||||
|
|||||||||||||||||||||||
Attachments & Links: |
|||||||||||||||||||||||
|
|
|
|||||||||||||||||||||
|
|
|
|||||||||||||||||||||