Approve award of Total Bid for Longview Road Water Transmission Main Extension – Project Three, Project No. 12-2013 / CIP No. 50900 opened on March 31, 2015, to the lowest responsible bidder, Mainline Contracting, Inc., in the amount of $1,857,477.25. |
|||||||||||||||||||||||
Summary: |
|||||||||||||||||||||||
The Project is based on the July 2009 report titled, “Final Water Supply Study Rapid City Regional Airport, Rapid City, South Dakota”, by KLJ and AE2S. A 16” PVC water transmission main is proposed to be extended from an existing 16” main on Homestead to the airport. The water transmission main will be bid under four separate projects. This project consists of approximately 13,300 feet of 16 inch water main, and associated appurtenances. This project is located in future Twilight Drive and Anderson Road. |
|||||||||||||||||||||||
Funding Source & Fiscal Impact (if applicable): |
|||||||||||||||||||||||
☒ Budgeted ☐ Not Budgeted |
|||||||||||||||||||||||
Recommendation: |
|||||||||||||||||||||||
Award: Total Base Bid in the amount of $1,857,477.25 to Mainline Contracting, Inc.. Notes: |
|||||||||||||||||||||||