CITY of RAPID CITY

Agenda Item Summary

 

Public Works Committee Meeting Date: 12/9/2014

City Council Meeting Date: 12/15/2014

Staff Contact: Rod Johnson

Petitioner: City of Rapid City

Location: 225 East Main St. North

 

Agenda Title:

Approve Change Order #1 to SECO Construction, Inc. for Utility Maintenance Facility, Project No. 13-2120 / CIP 50870 for an increase of $210,411.20. 

 

Summary:

Adjustment based on unit cost prices from 9000 CY of excavation and engineered fill to over 14,000 CY - $189,054.20.  Contaminated soils, debris, vapor barrier and piping - $20,144.00.  Miscellaneous - $1213.00                                                                                                                                                                                     

Funding Source & Fiscal Impact (if applicable):

 

Fund

Cost Center

 

Fund

Cost Center

Wastewater

Replace/Improve

 

 

 

Water

Replace/Improve

 

 

 

 

 

 

 

 

 

x

Budgeted

 

 

Not Budgeted

Recommendation:

Action: Approve

Notes:

City Council Options:

 

Attachments & Links:

Change Order

 

 

 

 

 

Click here to enter text.

Click here to enter text.

Click here to enter text.