CITY of RAPID CITY Agenda Item Summary |
|||
|
|||
Bid Opening Date: August 12, 2014 |
City Council Hearing: August 18, 2014 |
||
Staff Contact: Todd Peckosh |
|
||
|
|
||
Agenda Title: |
|||
Approve award of Schedule B Total Bid for Wildwood Drive Reconstruction Project – Phase 1, Project No. 13-2118 / CIP No. 50453 opened on August 12, 2014, to the lowest responsible bidder, Site Works Specialists, Inc., in the amount of $918,011.18. |
|||
Summary: |
|||
Reconstruction of Wildwood Drive from Sheridan Lake Road to approximately 800' west of Sheridan Lake Road. |
|||
Funding Source & Fiscal Impact (if applicable): |
|||
Streets 8910: Water 934: Drainage 8911: Sanitary 834: |
|||
Recommendation: |
|||
Award: Total Schedule B Base Bid in the amount of $918,011.18 to Site Works Specialists, Inc. Notes: NA |
|||
Options: |
|||
NA |
|||