CITY of RAPID CITY Agenda Item Summary |
|||
|
|||
Bid Opening Date: July 15, 2014 |
City Council Hearing: July 21, 2014 |
||
Staff Contact: Todd Peckosh |
|
||
|
|
||
Agenda Title: |
|||
Approve award of Total Bid for 2014 Bridge Repairs, Project No. 14-2171 / CIP No. 50445 opened on July 15, 2014, to the lowest responsible bidder, J V Bailey, Co. Inc., in the amount of $267,337.60. |
|||
Summary: |
|||
Project will replace pedestrian bridge between W. Chicago St. and W. Saint Louis St, and will repair bridge deck for 8th Street Bridge over Rapid Creek. |
|||
Funding Source & Fiscal Impact (if applicable): |
|||
STCM: 301: Streets: 8910 |
|||
Recommendation: |
|||
Award: Total Base Bid in the amount of $267,337.60 to J V Bailey Co., Inc. Notes: NA |
|||
Options: |
|||
NA |
|||