Agenda Title:

Approve Change Order No. 3F to Heavy Contractors for Roosevelt Park 50 Meter Pool, Project No. 13-2090 / CIP No. 50948, for an increase of $9,439.83.

Summary:

Final change order.     Final project cost: $4,598,892       Budget: $4,600,000

Funding Source & Fiscal Impact (if applicable):

 

Recommendation:

Action: Choose an item. Approve

Notes: Click here to enter text.

City Council Options:

Click here to enter text.

Attachments & Links:

Change Order

Click here to enter text.