CITY of RAPID CITY

Agenda Item Summary

 

Public Works Committee Meeting Date: 7/1/2014

City Council Meeting Date: 7/7/2014 Click here to enter date.

Staff Contact: Dan Coon

Petitioner: Click here to enter text.

Location: Water Reclamation Facility

 

Agenda Title:

Approve Change Order No. 1F to MAC Construction Company, Inc. for WRF Interim Trickling Filter Pump Station Improvements – Construction and Installation, Project No. 13-2105 / CIP No. 50966 to decrease the Contract Amount by $15,680.00 and Extend the Contract Time 14 days to November 15, 2013.

Summary:

The Contract Amount is reduced ($15,680.00) to reflect items not required on the project and the Contract Time is extended 14 days to November 15, 2013 to account for a delay in delivery of critical materials that was beyond the Contractor’s control.

 

Funding Source & Fiscal Impact (if applicable):

 

Fund

Cost Center

 

Fund

Cost Center

0604

0833

 

 

 

 

 

 

 

 

 

 

 

 

 



Recommendation:

Action: Choose an item. Approve

Notes:

City Council Options:

Approve or Reject

Attachments & Links:

Change Order

 

 

 

 

 