Approve Change Order #2 to Site Work Specialists, Inc. for Landfill Cell 16 Expansion Construction, Project No. 13-2111, for an increase of $70,976.65.
|
||||||||||||||||||
Summary: |
||||||||||||||||||
Increase to contract based on actual quantities installed. This increase is mainly due to the contractor needing to remove overburden on Johnson Property and place daily/intermediate cover on Cells 13/14. |
||||||||||||||||||