CITY of RAPID CITY Agenda Item Summary |
|||
|
|||
Bid Opening Date: April 15, 2014 |
City Council Hearing: April 21, 2013 |
||
Staff Contact: Michelle Schweitzer |
|
||
|
|
||
Agenda Title: |
|||
Approve award of Total Bid for West Chicago Street Utilities Breakout Project, Project No. 14-2161 / CIP No. 50448.1 opened on April 15, 2014, to the lowest responsible bidder, Mainline Contracting, Inc., in the amount of $968,995.55. |
|||
Summary: |
|||
This is for the construction of water and sewer mains in advance of the SDDOT reconstruction of West Chicago Street between Saint Onge Street to Deadwood Avenue. |
|||
Funding Source & Fiscal Impact (if applicable): |
|||
Sanitary Sewer – 0833 and 0834, Water - 0933 |
|||
Recommendation: |
|||
Award: Total Base Bid in the amount of $968,955.55 to Mainline Contracting, Inc. Notes: NA |
|||
Options: |
|||
NA |
|||
Attachments & Links: |
|||
|
|
|
|
|
|
|
|