CITY of RAPID CITY Agenda Item Summary |
|||
|
|||
Bid Opening Date: December 10, 2013 |
City Council Hearing: December 16, 2013 |
||
Staff Contact: Keith Winter |
|
||
|
|
||
Agenda Title: |
|||
Approve award of Total Bid for Concrete Panel Repairs, Project No. 13-2131 / CIP No. 50445 opened on December 10, 2013, to the lowest responsible bidder, Brewer Construction, in the amount of $76,384.54. |
|||
Summary: |
|||
Concrete panel repairs at various locations |
|||
Funding Source & Fiscal Impact (if applicable): |
|||
STCM: 301 |
|||
Recommendation: |
|||
Award: Total Base Bid in the amount of $76,384.54 to Brewer Construction. Notes: NA |
|||
Options: |
|||
NA |
|||
Attachments & Links: |
|||
|
|
|
|
|
|
|
|