CITY of RAPID CITY

Agenda Item Summary

 

Bid Opening Date: November 26, 2013

City Council Hearing: December 2, 2013

Staff Contact: Keith Johnson

 

 

 

Agenda Title:  

Approve award of Total Bid for Curtis Street Sanitary Sewer Replacement Project No. 12-2007 / CIP No. 50876 opened on November 26, 2013, to the lowest responsible bidder, Main Line Contracting, Inc., in the amount of $51,322.00.

Summary:

 

Funding Source & Fiscal Impact (if applicable):

Sanitary Sewer - 0833

Recommendation:

   Award:  Total Base Bid in the amount of $51,322.00 to Main Line Contracting Inc.