CITY of RAPID CITY Agenda Item Summary |
|||
|
|||
Public Works Committee Meeting Date: 8/27/2013 |
City Council Meeting Date: 9/3/2013 |
||
Staff Contact: Klare Schroeder |
Petitioner: |
||
Location: |
|
||
Agenda Title: |
|||
Change Order #1F to Goudy Engineering Inc for 30 Inch Steel Water Main CPS Rehabilitation, Project No. 11-2015 / CIP No. 50902, for an increase of $5,171.64. |
|||
Summary: |
|||
Increase to the contract amount based on actual quantities installed. |
|||
Funding Source & Fiscal Impact (if applicable): |
|||
0932 – Water Enterprise Fund |
|||
Recommendation: |
|||
Action: Approve Notes: |
|||
Options: |
|||
|
|||
Attachments & Links: |
|||
|
|
||
|
|
|
|
|
|
|
|