CITY of RAPID CITY Agenda Item Summary |
|||
|
|||
Bid Opening Date: August 27, 2013 |
City Council Hearing: September 3, 2013 |
||
Staff Contact: Rod Johnson |
|
||
|
|
||
Agenda Title: |
|||
Approve award of Total Base Bid plus Alternates 1, 2, 3, 4 and Allowance for Block 75 Parking Structure Maintenance/Repair Items, Project No. PR12-2041 / CIP No. 51001 opened on August 27, 2013, to the lowest responsible bidder, Scull Construction Service, Inc., in the amount of $233,400.00. |
|||
Summary: |
|||
Joint replacement, drainage improvements, surface repair, painting, re-striping |
|||
Funding Source & Fiscal Impact (if applicable): |
|||
PL&A - 871 |
|||
Recommendation: |
|||
Award Total Bid plus Alternates 1, 2, 3 and 4 in the amount of $213,400.00 to Scull Construction Service, Inc. Notes: NA |
|||
Options: |
|||
NA |
|||