Agenda Item Summary |
|||
|
|||
Bid Opening Date: July 30, 2013 |
City Council Hearing: August 5, 2013 |
||
Staff Contact: Louie Arguello |
|
||
|
|
||
Agenda Title: |
|||
South Berry Pines SS Extension Source Water Protection & W Main St SS Reconstruction Project No. 13-2072 / CIP No. 50549 |
|||
Summary: |
|||
S. Berry Pine Rd SS extension: starts at the existing sanitary sewer located in front 4720 Ridgewood St. The SS main will be extended 107 feet to S Berry Pine Rd and 520 ft NW on S Berry Pine Rd. W Main St: reconstruct approximately 1000 lineal feet of sanitary sewer main on W Main St between Edgewood Dr and S Berry Pine Rd. |
|||
Funding Source & Fiscal Impact (if applicable): |
|||
Sewer Expansion – 834 / Source Water Revolving – 834 / Water Expansion - 934 |
|||
Recommendation: |
|||
Award Total Bid in the amount of $547,244.00 to R.C.S. Construction, Inc. Notes: NA |
|||
Options: |
|||
NA |
|||
Attachments & Links: |
|||
|
|
|
|
|
|
|
|