CITY of RAPID CITY Agenda Item Summary |
|||
|
|||
Public Works Committee Meeting Date: 5/14/2013 |
City Council Meeting Date: 5/20/2013 |
||
Staff Contact: Mary Bosworth |
Petitioner: |
||
Location: |
|
||
Agenda Title: |
|||
Change Order #1F to Mainline Contracting Inc. for Arrowhead Drainage Basin Detention Cells 200 & 201 Maintenance, Project No. 12-2037 / CIP No. 50786, for an increase of $3,072.40. |
|||
Summary: |
|||
Increase in contract amount based on actual quantities used to complete the project. |
|||
Funding Source & Fiscal Impact (if applicable): |
|||
8911 |
|||
Recommendation: |
|||
Action: Approve Notes: |
|||
Options: |
|||
|
|||
Attachments & Links: |
|||
|
|
||
|
|
|
|
|
|
|
|