CITY of RAPID CITY Agenda Item Summary |
|||
|
|||
Meeting Date: 5/6/13 (City Council) |
Commission, Board or Committee: NA |
||
Staff Contact: Todd Peckosh |
PW Committee or L&F Committee: NA |
||
Petitioner: |
City Council Hearing: 5/6/13 |
||
Location: East North Street |
City Council 2nd Reading: NA |
||
Agenda Title: |
|||
No. CC050613-02.2 – East North Street Utility Reconstruction – Herman St to Pine St, Project No. 12-2017 / 50865 |
|||
Summary: |
|||
East North Street Utility Reconstruction – Herman Street to Pine Street. Project No. 12-2017 / CIP No. 50865. Opened on April 17 by SDDOT. |
|||
Funding Source & Fiscal Impact (if applicable): |
|||
933-4381-0602 = $1,012,272.64 |
|||
Recommendation: |
|||
Action: Award bid in the amount of $1,012,272.64. Notes: The SDDOT will consider awarding the associated grading project at their April 25 Commission meeting. |
|||
Options: |
|||
|
|||
Attachments & Links: |
|||
|
|
||
|
|
|
|
|
|
|
|