No. 08PL138 - East Mall Business Center Subdivision

A request by Ferber Engineering Co., Inc. for North Street Fire Station, LLC to consider an application for a Preliminary Plat on Lots 1 and 2 of Block 5 of East Mall Business Center Subdivision and dedicated public right-of-way for East North Street, Section 29, T2N, R8E, BHM, Rapid City, Pennington County, South Dakota, legally described as a portion of the SE1/4 north of Interstate 90 less Tract A of the NE¼ SE¼ and less lots H5, H6, H7, H8 and H9 but including that part of vacated East Mall Drive being part of the outside edge of Lot H5; and part of the SW¼ north of Interstate 90 including vacated East Mall Drive within said SW¼ and less Lot 1 of NE¼ SW¼ and less Lots 1 and 2 of NW¼ SW¼ and less Lot H5 and less lot H8; and part of Lot 1 of the NE¼ SW ¼ including vacated East Mall Drive within said Lot 1 and less Lot H7; and part of NW¼ including vacated East Mall Drive within said NW¼ less Lots AR, B, C and less E½ NE¼ NW¼ and less E½ NW¼ NE¼ NW¼ and less Lots H2 and H4; and part of Lot C of NW¼ less Lot H3 and less Lot H1; and part of Lot 1 of Silver Strike Subdivision; and all located in Section 29, T2N, R8E, BHM, Rapid City, Pennington County, South Dakota, more generally described as being located northwest of the intersection of East North Street and East Mall Drive.


PLANNING COMMISSION RECOMMENDATION:
Planning Commission recommended that the Preliminary Plat application be approved with the following stipulations:

1.

Prior to City Council approval of the Preliminary Plat application, all red lined comments made on the construction plans must be addressed and resubmitted for review and approval. In addition, the red lined drawings must be returned to the Growth Management Department;

2.

Prior to Final Plat approval, a different road name shall be submitted for review and approval for East North Street;

3.

Prior to Preliminary Plat approval by City Council, a cost estimate for the subdivision improvements reflecting the project phasing shall be submitted for review and approval;

4.

Prior to Preliminary Plat approval by City Council, an Erosion and Sediment Control Permit in compliance with the adopted Stormwater Quality Manual shall be submitted for review and approval;

5.

Prior to Preliminary Plat approval by City Council, revised construction plans identifying the phasing plans shall be submitted for review and approval;

6.

Upon submittal of a Final Plat application, surety for the lift station and force main improvements or alternative gravity sewer service and any required subdivision improvements that have not been completed shall be posted and subdivision inspection fees be paid as required;

7.

Prior to the City’s acceptance of the public improvements, a warranty surety shall be submitted for review and approval as required; and,

8.

The approved Preliminary Plat for which no grading, construction or other improvements have been initiated within two years of the date of approval of the plat shall be deemed as expired. However, the owner or applicant of the plat may, prior to the termination of the two year period, request a one year extension subject to approval by the City Council.

VOTE: (6 to 0 with Brewer, Brown, Hennies, Marchand, Rolinger and Scull voting yes and none voting no)