PUBLIC WORKS COMMITTEE RECOMMENDATION:
Public Works Committee recommended approval of the allocation of $1,000,000 from the .16 Utility Fund for the construction of a booster station, 750,000 gallon water reservoir, telemetry and 12” water main extending from the reservoir to St. Martin’s Drive with the intent that project be considered for incorporation into a bond sale as a potential means of repayment.
.16 Utility Fund Oversight Committee Recommendation:
Recommend approval of the allocation of $1,000,000 from the .16 Utility Fund for the construction of a booster station, 750,000 gallon water reservoir, telemetry and 12” water main extending from the reservoir to St. Martin’s Drive with the intent that project be considered for incorporation into a bond sale as a potential means of repayment.
VOTE:
(7 to 2 with
Hanks, Chapman, Hadcock, LaCroix, Brown, Elkins, and Jablonski voting yes and with Preston and Okrepkie voting no)
|