No. 06PL004 - Marlin Industrial Park A request by Dream Design International, Inc. to consider an application for a Preliminary Plat on Lots 1 thru 7 of Marlin Industrial Park, located in Lot A Lot A of the NE1/4 of the NW1/4 less Lot H1 and less the Right-of-Way and the unplatted portion of the NW1/4 of the NE1/4 of Section 20, T1N, R8E, BHM, Rapid City, Pennington County, South Dakota, legally described as Lot A of the NE1/4 of the NW1/4 less Lot H1 and less the Right-of-Way and the unplatted portion of the NW1/4 of the NE1/4 of Section 20, T1N, R8E, BHM, Rapid City, Pennington County, South Dakota, more generally described as being located at the southeast corner of the intersection of Elk Vale Road and Old Folsom Road. |
PLANNING COMMISSION RECOMMENDATION: |
|
1. |
An exception to the Street Design Criteria Manual to allow a cul-de-sac length to 1316 feet in lieu of 1200 feet in an industrial area and to allow more than 200 trips per day on the cul-de-sac is hereby granted; |
2. |
Prior to start of construction an Air Quality permit shall be obtained; |
3. |
Prior to Preliminary Plat approval by City Council, all necessary changes shall be made to the construction plans as identified on the redlined drawings. In addition, the redlined drawings shall be returned to the Growth Management Department; |
4. |
Prior to start of construction, access easements for utilities shall be obtained and recorded with the Register of Deeds and a copy shall be submitted to Growth Management; |
5. |
Prior to start of construction, a South Dakota Department of Transportation approach permit for Creek Drive shall be obtained and a copy submitted to Growth Management; |
6. |
Prior to start of construction, a grading permit from the South Dakota Department of Transportation for work in the right-of-way along Elk Vale Road shall be obtained and a copy submitted to Growth Management; |
7. |
Prior to Preliminary Plat approval by City Council, the Iowa, Chicago & Eastern Railroad Corporation shall enter into an agreement with the City of Rapid City to allow the construction of City water and sewer lines in the Railroad right-of-way. In addition the agreement shall be recorded at the Register of Deeds Office; |
8. |
Upon submittal of the Final Plat application, a cost estimate for the subdivision improvements shall be submitted for review and approval; and; |
9. |
Upon submittal of the Final Plat application, surety for any required subdivision improvements that have not been completed shall be posted and the subdivision inspection fees shall be paid. |
VOTE: (9 to 0 with Andrews, Brenneise, Brewer, Brown, Hennies, Landguth, LeMay, Schmidt and Waltman voting yes and none voting no)
|