No. 05PL123 - Pine Crest Village Addition A request by Kadrmas for Pine Crest Village Ltd. Ptnshp. to consider an application for a Preliminary Plat on Lot 2, Block 1, Pine Crest Village Addition located in the SW1/4, Section 13, T2N, R7E, BHM, Rapid City, Pennington County, South Dakota, legally described as a tract of land lying in the SW1/4 of Section 13, T2N, R7E, BHM, Rapid City, Pennington County, South Dakota, described more particularly as follows: commencing at the southeast corner of Lot 12, Block 6, of the plat of Lots 1 and 2 of Block 5, and Lot 12 of Block 6, Auburn Hills Subdivision; thence from said corner of S00º06’59”W for 100.20 feet to the point of beginning; thence from said point of beginning S86º46’09”E for 310.31 feet; thence S00º11’06”W for 285.66 feet; thence S89º53’47”W for 310.03 feet; thence N00º12’53”E for 303.71 feet to the point of beginning, said tract contains 2.097 acres, and, a tract of land lying in the SW1/4, Section 13, T2N, R7E, BHM, Rapid City, Pennington County, South Dakota, more particularly described as follows: commencing at the southeast corner of Lot 12, Block 6, of the plat of Lots 1 and 2 of Block 5, and Lot 12 of Block 6, Auburn Hills Subdivision which is the point of beginning; thence from said point of beginning S00º06’59”W for 100.20 feet; thence S00º12’53”W for 303.71 feet; thence S00º17’45”W for 263.17 feet; thence S89º57’16”W for 311.95 feet; thence N00º11’03”E for 300.82 feet; thence along a curve to the right with a delta angle of 40º01’24”, a radius of 174.00 feet and an arc length of 121.55 feet; thence N 40º12’27”E for 137.94 feet; thence along a curve to the left with a delta angle of 40º01’48”, a radius of 226.00 feet and an arc length of 157.90 feet; thence N00º10’4”E for 3.16 feet; thence N89º41’05”E for 130.11 feet to the point of beginning, said tract contains 3.975 acres, more generally described as being located at the southern terminus of Chalkstone Drive. |
PLANNING COMMISSION RECOMMENDATION: Planning Commission recommended that the Preliminary Plat be approved with the following stipulations: |
|
1. |
Prior to Preliminary Plat approval by the City Council, all necessary changes shall be made to the construction plans as identified on the red lined drawings. In addition, the red lined drawings shall be returned to the Growth Management Department; |
2. |
Prior to Preliminary Plat approval by the City Council, additional water information shall be submitted for review and approval demonstrating that sufficient domestic and fire flows are being provided during peak day use conditions; |
3. |
Prior to Preliminary Plat approval by the City Council, additional grading and drainage information shall be submitted for review and approval. In particular, the drainage plan shall include calculations demonstrating that discharge from any regional facilities will result in net drainage basin run-off not exceeding pre-development flow rates or local detention facilities shall be provided. In addition, the plat document must be revised to provide drainage easements as needed; |
4. |
Prior to Preliminary Plat approval by the City Council, a cost estimate of the subdivision improvements shall be submitted for review and approval; |
5. |
Prior to submittal of a Final Plat application, the plat title shall be revised to eliminate “Subdivision” and to add “a portion of the SW1/4 SW1/4, Section 13, T2N, R7E”; |
6. |
Prior to submittal of a Final Plat application, the plat document shall be revised removing the existing structure locations and landscaping from the plat document; and, |
7. |
Upon submittal of the Final Plat application, surety for any required subdivision improvements that have not been completed shall be posted and the subdivision inspection fees shall be paid. |
VOTE: (6 to 0 with Andrews, Anderson, Brown, Nash, Prairie Chicken and Schmidt voting yes and none voting no) |