No. 04PL046 - Section 11, T1N, R7E
A request by Wyss Associates, Inc. for Web Real Estate Holdings Co. to consider an application for a Layout Plat on property described by metes and bounds as commencing at the SW corner of the NW1/4 of the SE1/4 of Section 11, T1N, R7E, BHM, Rapid City, Pennington County, South Dakota, thence 1878.66 feet at a bearing S89º27'22"E to a point; thence 59.84 feet at a bearing N00º32'37"E to a point of beginning; thence travel 214.00 feet at a bearing N34º24'28"W to a point; thence travel 38.11 feet along a 210' radius concave southwesterly curve with a chord bearing N39º36'25"W, thence travel 166.06 feet at a bearing N44º48'23"W to a point; thence travel 333.97 feet along a 190' radius concave easterly curve with a chord bearing N05º32'55"E, thence travel 219.73 feet at a bearing N55º19'07"E to a point; thence travel 267.59 feet at a bearing S34º35'20"E to a point; thence travel 300.18 feet at a bearing S45º00'00"W to a point; thence travel 303.00 feet at a bearing S34º24'28"E to a point; thence travel 108.36 feet at a bearing S45º05'51"W to the point of beginning, more generally described as being located west of the western terminus of Fairmont Boulevard and north of Tower Road.


PLANNING COMMISSION RECOMMENDATION:
Planning Commission recommended that the Layout Plat be approved with the following stipulations:

1. Upon submittal of a Preliminary Plat, geotechnical information and slope stability analysis shall be submitted for review and approval;
2. Upon submittal of a Preliminary Plat, a grading plan shall be submitted for review and approval;
3. Upon submittal of a Preliminary Plat, a Drainage Plan designed in accordance with the Meade Hawthorne Drainage Basin Design Plan shall be submitted for review and approval. The drainage plan shall also identify off-site impacts. In addition, the plat document shall be revised to provide drainage easements as needed;
4. Upon submittal of a Preliminary Plat, road construction plans for Fairmont Boulevard shall be submitted for review and approval. In particular, the construction plans shall show the street located in a minimum 59 foot wide right-of-way and constructed with a minimum 26 foot wide paved surface, curb, gutter, street light conduit and sewer or a Variance to the Subdivision Regulations shall be obtained;
5. Upon submittal of a Preliminary Plat, the plat document shall be revised to provide a non-access easement along Fairmont Boulevard except for approved approach locations as per the Street Design Criteria Manual;
6. Upon submittal of a Preliminary Plat, sewer plans prepared by a Registered Professional Engineer showing the extension of sanitary sewer mains and service lines shall be submitted for review and approval or a Variance to the Subdivision Regulations shall be obtained;
7. Upon submittal of a Preliminary Plat, water plans prepared by a Registered Professional Engineer showing the extension of water mains shall be submitted for review and approval or a Variance to the Subdivision Regulations shall be obtained;
8. Upon submittal of a Preliminary Plat, a cost estimate of the subdivision improvements shall be submitted for review and approval; and,
9. Upon submittal of the Final Plat, surety for any required subdivision improvements that have not been completed shall be posted and the subdivision inspection fees shall be paid.

Vote: (7 to 0 Brown, Fast Wolf, Henning, Hoffmann, Nash, Prairie Chicken and Stone voting yes and none voting no)