PLANNING
COMMISSION RECOMMENDATION:
Planning Commission recommended that the Layout Plat be approved
with the following stipulations:
Engineering Division Recommendations:
1. Upon submittal of the Preliminary Plat, all necessary changes shall
be made to the construction plans as identified on the red lined drawings.
In addition, the red lined drawings shall be returned to the Engineering
Division;
2. Upon submittal of the Preliminary Plat, a pavement design with
supporting geotechnical information shall be submitted for review
and approval;
3. Upon submittal of the Preliminary Plat, a drainage study and grading
plan shall be completed to identify all street drainage improvements,
including but not limited to conveyance of existing flows across and
through the property, relocation of existing conveyances and in compliance
with the Flood Plain Ordinance and the City's Drainage Criteria Manual;
4. Upon submittal of the Preliminary Plat, the applicant shall enter
into a cost sharing agreement with the City for necessary off-site
water extensions to help extend the capacity of the existing Southwest
Pressure Zone System if this zone is needed to serve the development;
5. Upon submittal of the Preliminary Plat, sewer plans showing the
construction sewer mains within platted rights-of-way shall be submitted
for review and approval or a Variance to the Subdivision Regulations
shall be obtained;
6. Upon submittal of the Preliminary Plat, the plat document shall
be revised to show all easements for proposed and existing utilities
as indicated on the red lined plans;
7. Upon submittal of the Preliminary Plat, the plat document shall
be revised to show a non-access easement along Sheridan Lake Road
except for the approved intersection location. In addition, a non-access
easement shall be shown along double frontage lots requiring access
from the lesser order street and at all intersections as per the Street
Design Criteria Manual;
8. Upon submittal of the Preliminary Plat, complete engineering plans
as specified in Section 16.20.040 of the Rapid City Municipal Code
shall be submitted for review and approval. In particular, complete
street design plans shall be submitted showing the location of utilities,
storm drainage, curb and gutter and sidewalk improvements for all
adjacent and interior roadways. In addition, any Special Exception
requests to the Street Design Criteria Manual shall be clearly identified.
Any proposed phasing limits shall be submitted for review and approval
and identified on the construction plans;
9. Upon submittal of the Preliminary Plat, the construction plans
shall be revised to identify traffic controls at the three way intersection;
10. Upon submittal of the Preliminary Plat, the plat document shall
be revised to provide an additional 14 feet of right-of-way along
Sheridan Lake Road or a Variance to the Subdivision Regulations shall
be obtained;
11. Upon submittal of the Preliminary Plat, the construction plans
shall be revised to show South No Name Court and North No Name Court
as a minimum 49 foot wide right-of-way with a 24 foot wide paved surface;
12. Prior to Preliminary Plat approval by the City Council, a cost
estimate shall be submitted for review and approval;
13. Prior to the start of any construction within the area of the
property located within the 100 year federally designated floodplain,
a Letter of Map Revision shall be obtained from the Federal Emergency
Management Agency;
Fire Department Recommendation:
14. Upon submittal of the Preliminary Plat, the road construction
plans shall provide a minimum 92 foot diameter driving surface in
the proposed cul-de-sac(s);
Emergency Services Communication
Center Recommendation:
15. Prior to Final Plat approval, alternate road names for North No
Name Court and South No Name Court shall be submitted for review and
approval. In addition, the plat document shall be revised to show
the revised road names;
Urban Planning Division Recommendations:
16. Upon submittal of the Preliminary Plat, a phasing plan shall be
submitted identifying the connection through the site to Sheridan
Lake Road as a part of Phase One of the development. In addition,
the street connection shall be in place prior to the issuance of a
building permit;
17. Prior to Preliminary Plat approval by the City Council, a Major
Amendment to the Fairway Hills Planned Residential Development shall
be obtained to allow a townhome development in lieu of the previously
approved garden homes; and,
18. Prior to Final Plat approval by the City Council, surety for any
required subdivision improvements that have not been completed shall
be posted and the subdivision inspection fees shall be paid.
Vote: (6 to 0 with Brannan, Brown,
Fast Wolf, Hoffmann, Prairie Chicken and Schmidt voting yes and none
voting no)
|