Staff
recommends that the Preliminary and Final Plat be continued to the
September 15, 2003 City Council meeting as the stipulations of approval
have not been met.
PLANNING
COMMISSION RECOMMENDATION:
Planning Commission recommended that the Preliminary and Final
Plat be approved with the following stipulations:
Engineering Division Recommendations:
1. Prior to Preliminary Plat approval by the City Council, the plat
document shall be revised to show the 25 foot X 40 foot common access
easement as a "shared approach" or construction plans in
compliance with the City's Street Design Criteria Manual for the access
easement shall be submitted for review and approval;
2. Prior to Preliminary Plat approval by the City Council, verification
from Williston Basin Pipeline Company indicating that concurrence
with the relocated gas pipe line easement shall be submitted for review
and approval;
3. Prior to Preliminary Plat approval by the City Council, a cost
estimate of the subdivision improvements shall be submitted for review
and approval; and,
Urban Planning Division Recommendations:
4. Prior to Final Plat approval by the City Council, surety for any
required subdivision improvements that have not been completed shall
be posted and the subdivision inspection fees shall be paid.
Vote: (6 to 0 with Fast Wolf, Hoffmann,
Mickelson, Schmidt, Stone and Wevik voting yes and none voting no)
|