Staff
recommends that the Preliminary and Final Plat be continued to the
August 18, 2003 City Council meeting as the stipulations of approval
have not been met.
PLANNING
COMMISSION RECOMMENDATION:
Planning Commission recommended that the Preliminary and Final
Plat be approved with the following stipulations:
Engineering Division Recommendations:
1. Prior to Preliminary Plat approval by the City Council, the drainage
plan shall be revised as necessary to address City Engineering comments
and submitted for review and approval. In addition, the plat document
shall be revised to show drainage easements as needed;
2. Prior to Preliminary Plat approval by the City Council, the sewer
plans shall be revised as necessary to address City Engineering comments
and submitted for review and approval. In addition, a Master Plan
identifying future sewer stub-outs and extensions as red-lined on
the construction plans shall be submitted for review and approval;
3. Prior to Preliminary Plat approval by the City Council, the water
plans shall be revised as necessary to address City Engineering comments
and submitted for review and approval. In addition, a Master Plan
identifying future water stub-outs and extensions as red lined on
the construction plans shall be submitted for review and approval;
Fire Department Recommendation:
4. All Uniform Fire Codes shall be continually met;
Urban Planning Division Recommendations:
5. Prior to Preliminary Plat approval by the City Council, the plat
document shall be revised to include the extension of East Oakland
Street to Cambell Street or the right-of-way shall be created by "H
Lot(s)";
6. Prior to Preliminary Plat approval by the City Council, the plat
document shall be revised to show the labeling of the interior street
as "East Oakland Street";
7. Prior to Final Plat approval by the City Council, a subdivision
estimate form shall be submitted for review and approval;
8. Prior to Final Plat approval by the City Council, surety for any
required subdivision improvements that have not been completed shall
be posted and the subdivision inspection fee shall be paid; and,
South Dakota Department of Transportation:
9. Prior to Preliminary Plat approval by the City Council, an approach
permit shall be obtained for any proposed approach location(s) along
Cambell Street.
Vote: (9
to 0 with Fast Wolf, Hoffmann,
Mashek, Mickelson, Prairie Chicken, Schmidt, Stone, Wall and Wevik
voting yes and none voting no)
|