Staff
recommends that the Preliminary Plat be approved and that the Final
Plat be continued to the September 16, 2002 City Council meeting.
PLANNING
COMMISSION RECOMMENDATION:
Planning Commission recommended that the Layout, Preliminary and Final Plat be approved with the following
stipulations:
Engineering Division Recommendations:
1. Prior to Final Plat approval by the City Council, a geotechnical
report shall be provided for review and approval;
2. Prior to City Council approval of the Final Plat, the plat shall
be revised to reflect all required water utility easements subject
to review and approval by the Engineering Division;
3. Prior to Final Plat approval by the City Council, the applicant
shall submit revised engineering plans in accordance with the Engineering
Division review comments;
Fire
Department Recommendations:
4. Prior to the start of any building construction, fire hydrants
shall be installed and operational;
5. Prior to issuance of a Certificate of Occupancy, the facility(s)
addresses shall be posted;
6. Prior to Final Plat approval by the City Council, design plans
shall be submitted showing the location of a temporary road providing
an emergency access route from the current terminus of Mercury Drive
to the proposed terminus of Shad Street in accordance with the requirements
of the Fire Department;
7. Prior to the start of any building construction, all weather access
roads shall be constructed to the building sites;
Urban Planning Division Recommendations:
8. Prior to Preliminary Plat approval by the City Council, the subdivision
improvement estimate shall be provided for review and approval; and,
9. Prior to Final Plat approval by the City Council, surety for any
required subdivision improvements that have not been completed shall
be posted and all the subdivision inspection fees shall be paid. (7
to 0 with Hoffman, Mashek, Prairie Chicken, Schmidt, Swedlund, Stone
and Wevik voting yes and none voting no)
|