PLANNING COMMISSION RECOMMENDATION:
Planning Commission recommended
that the Layout, Preliminary and Final Plat be approved with the following
stipulations:
Engineering Division Recommendations:
1. Prior to Final Plat approval by the City Council, the plat shall
be revised to include the dedication of an additional 17 feet of right
of way along the Park Drive frontage and a triangular area of right
of way in the northwest corner of the intersection of Park Drive and
Wonderland Drive;
2. Prior to City Council approval of the Final Plat, a Subdivision
Improvements Estimate shall be submitted that includes the cost for
the mill and overlay of Park Drive for a minimum of 900 linear feet
of Park Drive. The overlay shall be required between stations 0+00
and 9+00 shown on the design plans;
3. Prior to City Council approval of the Final Plat, a Subdivision
Improvements Estimate shall be submitted that includes the cost for
a minimum of 200 linear feet of bike path along the Park Drive frontage
and for the repair and/or replacement of any existing sidewalk damaged
along Park Drive and Wonderland Drive as a result of the utility service
construction;
4. Prior to City Council approval of the Final Plat, the applicant
shall provide detailed traffic control plans for the proposed work
within the Park Drive right of way;
5. Prior to City Council approval of the Final Plat, the plat shall
be revised to include non-access easements along the frontage of Park
Drive and Wonderland Drive. The non-access easement shall extend along
the south lot line of Lot L for a minimum distance of 70 feet and
along the east lot line of Lot L & K for a minimum distance of
125 feet;
6. Prior to City Council approval of the Final Plat, the plat shall
be revised to include additional drainage easements on Lots F, G,
H and I;
7. Prior to City Council approval of the Final Plat, the design plans
shall be revised to include the provision of sidewalk along the Wonderland
Drive frontage or the applicant shall obtain a Subdivision Variance
waiving the requirement to construct the sidewalk;
8. Prior to City Council approval of the Final Plat, the design plans
shall be revised to include the provision of street lights and street
identification and regulatory signage in accordance with the Street
Design Criteria Manual;
Fire Department Recommendations:
9. Prior to the start of any building construction, fire hydrants
shall be installed and operational;
10. Prior to the start of any building construction, wildland fire
mitigation shall be completed as required by the Fire Department;
11. All provisions of the Uniform Fire Code shall be continually met;
Urban Planning Division Recommendations:
12. Prior to Final Plat approval, the applicant shall obtain approval
of the Final Planned Residential Development;
13. All provisions of the Off-Street Parking Ordinance and the parking
requirements included in the Street Design Criteria Manual shall be
continually;
14. Prior to Final Plat approval by the City Council, the subdivision
improvement estimate shall be provided for review and approval and
all the subdivision inspection fees shall be paid; and,
15. Prior to Final Plat approval by the City Council, surety for any
required subdivision improvements that have not been completed shall
be posted.
|