Staff Report | Vicinity Map | Aerial Photograph | Site Plan |
No.
01UR060 - Red Rock Estates
A request by Dream Design International to consider an application for a Use
On Review to allow a utility substation in the Low Density Residential District
on NE1/4 SW1/4 Section 29, T1N, R7E, BHM, Rapid City, Pennington County, South
Dakota, more generally described as being located north of Prestwick Road north
of Countryside Subdivision.
PLANNING
COMMISSION RECOMMENDATION:
Planning Commission recommended that the
Use On Review to allow a utility substation in the Low Density Residential
District be approved with the following stipulations:
Engineering Division Recommendations: |
|
1. |
Prior to City Council approval, the applicant shall sign an agreement identifying the commitment to transfer ownership and maintenance of the water booster station to the City; |
2. |
Prior to City Council approval, a utility easement shall be recorded at the Register of Deed’s Office for the booster station and for the corresponding water lines to and from the site; |
3. |
Prior to City Council approval, the construction plans shall be revised to show a sidewalk along the front lot line; |
Fire Department Recommendations: |
|
4. |
All Uniform Fire Codes must be continually met; |
5. |
Prior to issuance of a Certificate of Occupancy, the facility’s address shall be posted. Said numbers shall be a minimum of seven inches in height and displayed on a contrasting background; |
Air Quality Division Recommendation: |
|
6. |
An Air Quality Permit shall be obtained prior to any development work or construction in excess of one acre; |
Urban Planning Division Recommendations: |
|
7. |
The proposed structure shall conform architecturally to the plans and elevations submitted as part of this Use on Review; |
8. |
Prior to City Council approval, the site plan shall be revised to comply with all provisions of the Off-Street Parking Ordinance; and, |
9. |
The Use on Review shall expire if the use for which it was granted has ceased for a period of two years or more. In addition, any other use of the property other than a utility substation shall require a Major Amendment to the Use on Review. |
VOTE: (10 to 0)