No. 05PL080 - Atlantis Subdivision
|
PLANNING COMMISSION RECOMMENDATION: Planning Commission recommended that the Layout Plat be approved with stipulations: |
|
1. |
Upon submittal of a Preliminary Plat application, a grading plan and an erosion and sediment control plan for all improved areas shall be submitted for review and approval; |
2. |
Upon submittal of a Preliminary Plat application, a drainage plan shall be submitted for review and approval. In addition, the plat document shall be revised to provide drainage easements as necessary; |
3. |
Upon submittal of a Preliminary Plat application, sewer plans prepared by a Registered Professional Engineer showing the extension of sanitary sewer mains and service lines shall be submitted for review and approval or a Variance to the Subdivision Regulations shall be obtained. In addition, the extension of water main(s) outside of public right-of-way will require that they be located in a “public utility easement” either by amending the plat document to show the easement(s) or a miscellaneous document shall be recorded at the Register of Deed’s Office creating the easement(s); |
4. |
Upon submittal of a Preliminary Plat application, water plans prepared by a Registered Professional Engineer showing the extension of water mains shall be submitted for review and approval or a Variance to the Subdivision Regulations shall be obtained. In addition, the extension of water main(s) outside of public right-of-way will require that they be located in a “public utility easement” either by amending the plat document to show the easement(s) or a miscellaneous document shall be recorded at the Register of Deed’s Office creating the easement(s); |
5. |
Upon submittal of a Preliminary Plat application, road construction plans for Elk Vale Road shall be submitted for review and approval. In particular, Elk Vale Road shall be constructed with a minimum 40 foot wide paved surface, curb, gutter, sidewalk, street light conduit, water and sewer or a Variance to the Subdivision Regulations shall be obtained; |
6. |
Upon submittal of a Preliminary Plat application, road construction plans for the I-90 service road shall be submitted for review and approval. In particular, the I-90 service road shall be constructed with a minimum 26 foot wide paved surface, curb, gutter, sidewalk, street light conduit, water and sewer or a Variance to the Subdivision Regulations shall be obtained; |
7. |
Upon submittal of a Preliminary Plat application, a cost estimate of the subdivision improvements shall be submitted for review and approval; |
8. |
The International Fire Code shall be continually met; |
9. |
Prior to submittal of a Final Plat application, a miscellaneous document or an “H Lot” shall be recorded at the Register of Deed’s Office securing the proposed access easement as legal access to the site; |
10. |
Prior to submittal of a Final Plat application, the plat document shall be revised to show a non-access easement along Elk Vale Road and the I-90 service road except for approved approach location(s); and, |
11. |
Upon submittal of a Final Plat application, surety for any required subdivision improvements that have not been completed shall be posted and the subdivision inspection fees shall be paid. |
VOTE: (6 to 0 with Andrews, Brown, Fast Wolf, Hadcock, Nash, and Prairie Chicken voting yes and none voting no) |
|