CITY of RAPID CITY

Agenda Item Summary

 

Public Works Committee Meeting Date: 3/15/2016

City Council Meeting Date: 3/21/2016

Staff Contact: Klare Schroeder

Petitioner: Click here to enter text.

Location:

 

Agenda Title:

Change Order No. 1 to Simon Contractors DBA Hills Materials Company for St Andrew and St Charles Street Sanitary Sewer and Water Reconstruction Project, Project No. 14-2168 / CIP No. 50959, for an increase of $17,214.44.

 

Summary:

Increase to contract based on actual quantities installed.

Funding Source & Fiscal Impact (if applicable):

 

Fund

Cost Center

 

Fund

Cost Center

Water

Replace/Improve

 

Wastewater

Replace/Improve

CIP

Streets

 

CIP

Drainage

 

 

 

 

 

 

x

Budgeted

 

 

Not Budgeted

Recommendation:

Action: Approve

Notes:

City Council Options:

 

Attachments & Links:

Change Order

 

 

 

 

 

Click here to enter text.

Click here to enter text.

Click here to enter text.