Agenda Title:  

Approve award of Total Schedule A and B for Concrete Panel Repairs, Project No. 13-2131 / CIP No. 50445 opened on July 28, 2015 to the lowest responsible bidder, Stanley J Johnsen Concrete Contractors, Inc, in the amount of $162,870.20.

Summary:

Concrete Panel Repairs along W. Chicago Street.

Funding Source & Fiscal Impact (if applicable):

Fund

Cost Center

 

Fund

Cost Center

Streets

8910

 

STCM

301

 

 

 

 

 

 

 

 

 

 

 

Budgeted      Not Budgeted

Recommendation:

   Award:  Total Schedule A and B in the amount of $162,870.20 to Stanley J Johnsen Concrete Contractors, Inc.