No. 05PL030 - Crystal Dome Subdivision

A request by Fisk Land Surveying & Consulting Engineers, Inc. for Craig Erickson to consider an application for a Layout Plat on Lot 1 of Crystal Dome Subdivision and dedicated right-of-way located in the E1/2 NE1/4 NE1/4 Section 13, T1N, R8E, BHM, Pennington County, South Dakota, legally described as E1/2 NE1/4 NE1/4 Section 13, T1N, R8E, BHM, Pennington County, South Dakota, more generally described as being located south of Long View Road along Radar Hill Road.


PLANNING COMMISSION RECOMMENDATION:
Planning Commission recommended that the Layout Plat be approved with stipulations:

1.

Prior to Layout Plat approval by the Planning Commission, a Master Plan for the balance of the subject property shall be submitted for review and approval;

2.

Upon submittal of a Preliminary Plat application, sewer plans prepared by a Registered Professional Engineer showing the extension of sanitary sewer mains and service lines shall be submitted for review and approval or a Variance to the Subdivision Regulations shall be obtained. If individual on-site wastewater systems are proposed, then percolation information demonstrating that the soils are suitable for on-site wastewater systems shall be submitted for review and approval;

3.

Upon submittal of a Preliminary Plat application, water plans prepared by a Registered Professional Engineer showing the extension of water mains shall be submitted for review and approval or a Variance to the Subdivision Regulations shall be obtained. If on-site well(s) are used, data to confirm that the well(s) have sufficient flows and water quality shall be submitted for review and approval. If a shared well is proposed then it shall be designed as a public water system. In addition, the plat document shall be revised to show utility easement(s) as needed;

4.

Upon submittal of a Preliminary Plat application, road construction plans for Radar Hill Road shall be submitted for review and approval. In particular, the road construction plans shall show Radar Hill Road constructed with a minimum 40 foot wide paved surface, curb, gutter, sidewalk, street light conduit, water and sewer or a Variance to the Subdivision Regulations shall be obtained;

5.

Upon submittal of a Preliminary Plat application, the plat document shall be revised to show an on-site fire apparatus turnaround easement as per the Fire Department;

6.

Upon submittal of a Preliminary Plat application, a cost estimate of the subdivision improvements shall be submitted for review and approval;

7.

The International Fire Code shall be continually met;

8.

Upon submittal of a Final Plat application, a note shall be placed on the plat indicating that at the time a Building Permit is applied for, a reserve drainfield area will be identified and held in reserve unless a public sewer system is provided; and,

9.

Upon submittal of a Final Plat application, surety for any required subdivision improvements that have not been completed shall be posted and the subdivision inspection fees shall be paid.

VOTE: (7 to 0 with Anderson, Brown, Fast Wolf, Hadcock, LeMay, Prairie Chicken and Schmidt voting yes and none voting no)